Bathroom equipments are installed

PA300008 PA300009

The bathroom equipments are installed. All are American Standard, and sensor activated faucets are being used for hygenic reasons.

Kitchen Appliances are installed

PA300007

Refrigirator, Oven, Microvawe, Dishwasher and Icemaker are purchased and installed

Kitchen and Bathroom Tiles are completed

Kitchen and Bathroom Tiles are completed. The bathroom wall porcelain tiles are installed up to 52" with a border.

Ataturk corner wall completed

PA240042

Ataturk corner is completed. The wall is covered by sparkling black granite

Stage soffit

The soffit of dance stage is completed.

Partitions

Bathroom area wall frame Kitchen area wall frame

The Light-gage stud partitions are installed. Ready for inwall pipes and conduits, prior to sheet rock (gypsum panel) installation

Slab of wet areas is cast

Concrete slab is poured at wetarea

The concrete at bathroom and kitchen area is poured as of Aug. 10, 2009.

Rough-in is completed as of July 31, 2009

Tary and drain for A/C units HVAC Unit w/ ducts

The roughin works of Mechanical, Plumbing and Electrical are completed as of July 31st.

Construction Started as of July 17, 2009

Turkevi Sign 011

The construction of Built-out Turkish Center Built-out started as of July 17th, 2009, upon receiving the permit from the city.
The permit and our "Turkevi" sign are posted. The trush container, and portable WC were placed.

Permit is received as of July 16, 2009

Atilla Orkan(FTCF VP) and Serap Odabas-Yigit(FTAA P)

The permit for built-out was received as of today, July 16th 2009